The Interconnection Queue Is the New Equipment Lead Time
Grid interconnection now takes longer than equipment. What data center buyers should know about powered land, utility capacity, and the secondary market.
By John Foster, Vice President, Global Procurement · · 6 min read

Procurement teams spent the last two years learning to live with multi year waits for transformers, switchgear, and generators. That lesson is about to repeat itself one layer up the stack. Getting the equipment delivered no longer guarantees a hall can open, because the utility connection that energizes it is now the longer wait of the two. For a growing number of buyers, the practical answer is the same one that worked for equipment: stop waiting in the primary queue and go find a position, a site, or a capacity block that already exists.
The wait is now measured in years, not months
JLL's 2026 Global Data Center Market Outlook, published January 5, 2026, states plainly that "the average wait time for a grid connection in primary data center markets exceeds four years." The same report calls energy infrastructure "the critical bottleneck constraining expansion" and says "speed to power is the primary criteria driving site selection," ahead of cost or location.
Lawrence Berkeley National Laboratory's Queued Up research tracks this directly, and the 2025 edition of that work, summarized by the trade publication Public Power, puts the timeline in concrete terms: the median time from submitting an interconnection request to signing an interconnection agreement ran "well over 3 years in 2025," and "the timeline to reach commercial operations exceeds 5 years" for the regions with available data. That is the generation side of the queue, which includes the new gas and renewable capacity data centers increasingly contract for directly, so it matters even to buyers who never touch a substation themselves.
The backlog behind those wait times is enormous and growing, even as some of it clears out. LBNL's data puts total capacity actively seeking interconnection at 2,061 gigawatts in 2025, down about 10 percent from a peak of nearly 2,600 gigawatts at the end of 2023, mostly because more projects are getting withdrawn than are getting built. ERCOT alone, the grid operator covering most of Texas, carried 408 gigawatts of that national backlog, the largest single regional share LBNL tracked.
Texas shows what the backlog looks like up close
Texas is a useful case study because the state has been unusually public about the scale of the problem. The Texas Tribune reported that ERCOT's April 2026 preliminary forecast projects a 2032 peak load of 367,790 megawatts, compared with the grid's actual record peak of 85,508 megawatts set in August 2023. At a June 2, 2026 board meeting, ERCOT CEO Pablo Vegas said the forecast is largely driven by "over 250,000 megawatts of forecast demand from large load projects." According to ERCOT's own figures, about 70 percent of those large load requests are data centers.
The queue grew faster than ERCOT's process could handle it. The grid operator's existing one at a time review was built, in the words of Texas Advanced Energy Business Alliance's Matthew Boms, for a world of "40 to 50 large load projects," not the 225 new interconnection requests ERCOT received in 2025 alone, per a December 2025 report cited by the Tribune. On June 2, 2026, ERCOT's board voted to start a new batch review process, nicknamed Batch Zero, that will first study proposals that have already secured financing and land, meaning the projects furthest along get studied first and everyone else keeps waiting.
That is the key fact for a buyer to internalize: queue reform does not create more capacity or move your project to the front. It sorts who gets studied first. A project with financing and land already secured jumps the line by design. A project without either stays where it is.
Why powered land costs what it costs
That dynamic shows up directly in land prices, and the premium is now large enough to measure. Avison Young's Q2 2026 Data Center Market report, cited by Data Center Knowledge, found that spending on land for future data centers reached roughly 6 billion dollars in the first half of 2026, up 79 percent year over year. In Northern Virginia, Avison Young's John Andril told the publication that entitled land without a secured power path sells for roughly 4 million dollars an acre, while comparable land with power secured sells for at least 6 million dollars an acre, a premium of 50 percent or more just for the connection. Andril said the gap is proportionally larger in lower cost markets, where land that might otherwise sell for around 10,000 dollars an acre can reach six figures an acre once a viable power path and utility relationship are in place.
A separate analysis by Altus Group, covering 80 verified data center land transactions, found that committed utility load was the single strongest predictor of price, and that sites tied to 230 kilovolt or 500 kilovolt transmission infrastructure traded at roughly 2.4 times the price of sites tied to 138 kilovolt or lower infrastructure. In plain terms, buyers are not paying for acreage anymore. They are paying for a place in line that someone else already earned.
What this means for sourcing, and the diligence it demands
The equipment market already showed the pattern: when OEM lead times blow out, buyers who can source a unit someone else already has in hand close the gap in weeks instead of years. Power and land are following the same path, through sellers who hold an advanced queue position, a signed utility agreement, or a site with transmission already in place, and would rather monetize it or partner on it than wait out a multi year build themselves.
The diligence is different from an equipment purchase, and buyers who treat it the same way get burned. Utility capacity rights generally arise from contracts and tariffs with the utility, not from a recorded real property interest, so a power position does not automatically transfer with a land sale. Assignment typically requires the utility's consent, and that consent process has its own timeline and conditions worth confirming before a deal closes, not after. A signed interconnection or electric service agreement is a materially different asset than a queue position alone; ask specifically which one is on the table, what milestones and deposits transfer with it, and whether the utility has acknowledged the transfer in writing. If the answer to any of those is vague, price the deal as a queue position, not as secured power, no matter what the seller calls it.
Confirm the voltage class and substation proximity behind any claim of "powered" land, since the Altus Group data above shows how much that detail moves price. Ask for the actual interconnection study results or system impact study, not a summary. And treat the financing and land status of a project the way ERCOT's Batch Zero now treats it: as the thing that determines whether you are near the front of the queue or still waiting behind it.
None of this makes the interconnection queue shorter. It does mean a buyer who sources the right position, site, or capacity block through the secondary market can open a facility years ahead of a buyer who starts a fresh application today. Post what you are sourcing, whether that is a powered site, an assignable utility capacity position, or the generation and transformer equipment to back it up, at supplyvaultai.com/buyers, and get matched to sellers who already hold what the queue is making everyone else wait years for.